Jeremy Gaston | Reporter

Much of the county will see some sort of delay in their daily commute in the coming weeks, if they haven’t already. Resurfacing work on K-31 between Osage City and US-75 is already underway, and will soon begin on a 26-mile stretch of US-56.

The K-31 resurfacing began July 11, starting with the most inconvenient portion of the project – the junction with US-75.

“We coordinated with Kansas Highway Patrol at the intersection,” said Earl Bosak, area engineer for the Kansas Department of Transportation. “They did that first to get it out of the way.”

Flag crews and pilot cars affected traffic on both highways Monday, but had moved off US-75 after completing heater scarification on the adjacent stretch of K-31. The process scrapes up a layer of existing asphalt, heats and mixes the rock and oil, and relays a rejuvenated surface in a single pass from several trucks.

The K-31 project was scheduled to be completed last year, but was postponed when funds sank and prices skyrocketed.

“Because of the price of oil, they couldn’t go as far last year,” Bosak said. “We got another group of funds [this year] and that was on the top of the list.”

The funds to pay for the project came from KDOT’s substantial maintenance funds, classified as a 1R project.

“They’re resurfacing projects we do every year,” Bosak said.

Bosak said the only additional delay on US-75 would be when the contractor, Dustrol, Inc., goes back over the surface with chip seal.

“The heater scarification has to be done for 10 days before the chip seal,” Bosake said. “The chip sealing will affect US-75 for just a couple hours.”

Dustrol’s contracted cost for the project is $714,096, and has a scheduled completion of “late July.” The project also includes K-31 north from Osage City to US-56 junction.

“They should probably be done with the heater scarification by the end of this week,” Bosak said. “Then they’ll wait a week and come back and put the chip-seal on, and that’ll take two or three days at the most.”

Work on US-56 was scheduled to begin Monday, but was delayed by a reordering of projects by Heckert Construction.

“The contractor decided to do K-130 in Lyon County first,” Bosak said. “It’s going to take a couple of days to do that, and it will probably be Friday or Monday before they get to US-56.”

The resurfacing on US-56 involves a larger stretch of road, but simpler technique, calling only for a chip seal resurfacing. The project has a $596,443 price tag and a mid-August completion date. Bosak indicated that once started, the project could be completed within a couple of weeks.

“Chip seal goes pretty fast,” he said. “They spray oil on the surface of the road, and put a rock chip on top to give it a surface.”

Both projects will be completed one lane at a time, allowing traffic to flow with the use of pilot cars. There will be no posted detours.

“If locals know a detour, take it,” Bosak said. “Otherwise, we’ll tell them to go through the project like normal, they’ll just have a 10 to 15 minute wait.”