Burlingame unhappy with water project

Gabe Faimon |
Reporter

BURLINGAME—After earlier withholding payments to contractors due to dissatisfaction of work on Burlingame’s water system improvement project, city council members decided last week to submit written notice of the city’s concerns to bonding firms.

During a March 19 special meeting, the council met with U.S. Department of Agriculture (USDA) representative Daniel Fischer and Governmental Assistance Services representative Donna Crawford to discuss contractors’ performance on the project. No contractor representatives were present.

Bartlett & West had contracted to engineer and oversee the project, and J&H Construction, Inc. had contracted for construction and installation of water lines, meters and hydrants. Funding for the project was obtained through a $400,000 community development block grant from the Kansas Department of Commerce, linked with a USDA Rural Development loan. Contracts established Jan. 31 as the date for substantial completion of the project, but at the request of both contractors, the city agreed to extend the date to Feb. 26.

Discussed at the special meeting were contractor performance concerns that had first surfaced during a Feb. 24 final walk-through inspection of the project.

An inspection report prepared by Bartlett & West listed a total of 59 discrepancies including fire hydrants set at improper depth; old fire hydrants not removed; steel, instead of nonmetallic, covers installed on water meter boxes equipped with electronic reading devices; improper placement of water meters; improper placement of wires for electronic meter reading; blocked street drainage; pavement damage; improper valve installation; old water lines not taken out of service; and incomplete construction debris removal.

Subsequent inspections by city staff resulted in a report covering additional contractor performance deficiencies similar to those discovered during the walk-through inspection. Burlingame utility foreman Gerry Grandstaff reported that insufficient quantity of crushed rock was discovered at 13 of 20 hydrant installations, resulting in noncompliance with contract specifications. Also reflected in Grandstaff’s report was that water had not been supplied to one fire hydrant. The city’s inspection cited seven locations where duct tape was used to cover damage to buried telephone cable, although contract specifications called for damaged electrical lines to be spliced. Also cited were numerous locations where steel bolts were used to secure buried water line connections, instead of stainless steel fasteners as per contract specifications.

A March 9 telephone call by the Osage County Herald-Chronicle to Robert Helton, president of J&H, requesting comment regarding the identified deficiencies, has not been returned.

In a March 10 letter to J&H, city attorney Rick Godderz said, “I am enclosing a copy of a list compiled by the City identifying problems with the work performed in the installation of the water lines in the City. There are five pages of this list.”

A reply to Godderz’ letter had not been received by the city by March 19.

During last week’s special meeting, council members complained the project had not been completed by the contracted completion date.

“All of the old mains are still active, so work is not complete,” said council member Vikki DeMars.

Other council complaints were lack of oversight during the project.

“If he, the inspector, had read the contract, then we wouldn’t have to be here,” said council member Dustin Swander.

Fischer agreed. “I’m very disappointed as well,” he said. “It all falls back on the inspector.”

During a Feb. 9 council meeting, Burlingame Mayor Brenda Dorr noted that Bartlett & West’s contract required a project representative to prepare daily reports and maintain a logbook of inspections. Dorr said then that daily reports would serve as a resource for evaluation of contractors’ performance, and asked Bartlett and West representative, Lavene Brenden, if the documents could be made available for city review.

Last Thursday’s meeting concluded with council agreement that contractor performance had not been satisfactory, contract requirements remain unfulfilled and the project was not complete. It was decided the city must notify bonding firms of the city’s contractor performance concerns.

During the March 16 council meeting, the council discussed a letter from Developers Surety and Indemnity Company, dated March 10, stating the firm was furnishing the bond for the city’s construction contract with J&H, and had received a claim against the payment bond of J&H by a supplier of material. Developers Surety requested the city not release any additional funds to J&H without written consent of the firm.

“Material suppliers have contacted the city, so has the bonding company,” Godderz said. “The city will withhold payment for defective work.”

The council also considered citizen complaints received during the project. Two citizens had complained in February that water meters that had been shut off were later turned on, flooding a basement at one location and property at another. Another citizen complained of lack of contractor efforts to control erosion and repair driveway and ditch damage.

During that meeting, the council questioned Brenden about the project.

“Do you feel like the work has been done satisfactorily?” Swander asked.

“The majority,” Brenden replied.

Dorr commented that both firms had been requested to have a representative at the meeting, although no J&H representative was present.

Bartlett & West and J&H had jointly submitted a partial payment request for $74,204.95 on Feb. 26. The USDA loan requires payment requests to include the contractor’s certification that payment estimates have been completed in accordance with the contract, and the engineer’s certification that quantities are correct and work had been performed in accordance with the contract.

Excluding the Feb. 26 request, a total of $516,559.60 has been jointly requested by the contractors. City records show that since May 19, 2008, Bartlett & West has received $121,078.78 in eight payments from the city. A March 2 payment for $18,175.25 remains under review.