|
|
 |
Auburn Road travelers
notified of upcoming closures
Gabe Faimon
Special to the Herald-Chronicle
AUBURN—Rural Auburn residents and commuters to and from
Burlingame will likely be inconvenienced during bridge construction
on Auburn Road, but they have more than a year to prepare for it.
Planning details for closure of the road south of Auburn during
the summers of 2010 and 2011 were presented during a meeting in
the Auburn Civic Center Oct. 21.
Tom Black, of Shawnee County Public Works, said two Shawnee County
bridges immediately south of Auburn are structurally deficient and
must be replaced. In addition, David Jacobson, of the Kansas Turnpike
Authority (KTA), said that a portion of the deck of the KTA bridge
crossing the turnpike had failed and has been temporarily repaired.
Engineering studies conducted by the KTA concluded the bridge support
structure was sound, but the deck must be replaced.
Construction of each of the three bridges was completed in 1948
in preparation for construction of the Kansas Turnpike. Currently,
each of the bridges carries an average of 2,000 vehicles per day.
Representatives of both agencies agreed it would be desirable to
disrupt traffic only once, while construction on all three bridges
occurred simultaneously. However, Kansas law requires that all residences
affected by road repairs must have road access at all times.
Due to the location of three residences between the Wakarusa River
and the turnpike, the work must be split into two phases to allow
those residents access.
The first phase, replacing the two Shawnee County bridges, is tentatively
projected to begin in March 2010 with completion in July 2010. This
phase would allow access for the three residences south of the construction
zone.
Phase 2, replacing the deck of the KTA bridge, is tentatively projected
to begin in March 2011, with completion in June 2011. Following
completion of Phase 1, the second phase will allow access for the
three residences north of the construction zone.
The officials said state law does not allow detours that route traffic
from paved, all-weather roads to unpaved roads. Therefore, the official
detour can only include available paved roads. Since Burlingame
Road north of Burlingame does not connect with a paved east-west
road to link traffic, it cannot be included as part of the official
detour. East-west traffic will be routed on U.S. Highway 56 between
Burlingame and the intersection of U.S. 56 and Topeka Boulevard
(old Highway 75); and on 93rd Street between the intersections of
Topeka Boulevard and 93rd Street and Auburn Road. North-south traffic
will be routed on U.S. 56 and Topeka Boulevard and 93rd Street.
During the question and answer session, Burlingame Mayor Brenda
Dorr expressed concern regarding negative impact of the detour on
Burlingame, particularly area residents who commute to and from
west Topeka, and Allen Community College students who commute to
and from west Topeka to Burlingame.
Discussion also focused on increased traffic on Burlingame Road
in Osage County and Auburn Road in Shawnee County during the past
10 to 15 years and the resulting need for a turnpike tollgate south
of Auburn.
Representatives of the KTA said that a cost-benefit study of the
issue, conducted in 2006, did not provide favorable evidence that
construction would be a good investment for the KTA, for the construction
cost – estimated at $10-12 million - and operating cost must
be covered by revenue generated from tolls. Discussion then turned
to the possibility of joint funding between the KTA and jurisdictions
benefiting from the venture.
The meeting concluded with recognition of the need for all affected
jurisdictions to work together to conduct long-range planning that
would effectively address expected population and economic growth,
increased traffic on Auburn and Burlingame roads, and establishment
of a gate near Auburn for access to the turnpike.
The meeting was hosted by the city of Auburn, with Shawnee County
Commissioner Shelly Buhler convening the meeting.
Details regarding the construction projects and detour are anticipated
to be addressed in a public meeting early in 2010, approximately
six to eight weeks before the scheduled start of the first phase
of the project. |
|
 |
|